问题:

[单选题] Your project is behind schedule due to conflict between team members. Having resolved the conflict,to get the project back on schedule,you should consider ( ) .

A.crashing the schedule

B.performing resource leveling

C.conducting reverse resource allocation scheduling

D.utilizing the critical chair resources

答案解析: